Oil & Gas Journal’s Daily Update Newsletter on August 30, 2024, they
had an article titled, “Golden Pass LNG requests 3-year extension to 2029.” The article was on Golden Pass LNG was in the
news again this time requesting the U.S. Federal Energy Regulatory Commission
(FERC) for a three-year extension to get their LNG plant near Port Arthur,
Texas up and exporting by the end of November 2029. The Golden Pass LNG is a partnership
between ExxonMobil Corp. and QatarEnergy, and they have had a few hiccups since
work started in 2019. The latest was its
leading contractor being allowed to withdraw from the project due to its
bankruptcy. Golden Pass LNG has named
a new lead contractor, CB&I, who was part of the early team which worked on
the front-end engineering (FEED) and plans for the plant with Chiyoda Corp. The LNG plant has over three quarters of the
work done on its three-train plant.
Train 1 has utility and export groundwork in place, and it is over
three-quarters complete; Train 2 has just under half completed; and Train 3 is
about a third completed. If the FERC
request is granted, the new in-service dates would be roughly 18 months later
which would mean Train 1 would be exporting by March 31, 2027, and the other
two would follow suit, and the whole plant would be completed and exporting by
November 30, 2029. We will keep you
posted on Golden Pass LNG, when a decision comes down. If you would like more information on this
article from Oil and Gas Journal, please click the links: Golden
Pass LNG requests 3-year extension to 2029 | Oil & Gas Journal (ogj.com).
Don’t forget to check out our ESC's website or contact us via the email in the
blog, if you have a midstream logistics project you would like to
see get off the ground!